July 18, 2008 Building Update

More concrete was poured today! The concrete work is usually done in three stages, first the footings, then the foundation walls and then the slab (floor). We have not finished all the footings yet, but we were able to start pouring some of the foundation walls today. We expect more concrete work to be completed next week.

As for the mortgage, it has been a week of supplying additional information to the bank and now they will be ready to present our information to their committee on  next Tuesday, July 22.  I know, another delay, but on the bright side we now have more time to raise the cash needed for the closing . Please keep this in your prayers. I am confident that after Tuesday we will be able to set another closing date, hopefully between  July 28 and August 1. 