August 20, 2008 Building Update

We have  alot of good news to report!

The new mortgage closing date is currently scheduled for 8/28/08.

The shortage in our “cash on hand” requirement is down to $14,000.00, so after this weekends offering we will be good for the closing.

More of the concrete foudation walls were poured today. The estimated completion date of the foudation is 8/29/08.

Alot of lumber has been delivered to our building site this week.  Sections of the wood are currently being assembled.  During the week of 9/08/08, the wood frame of the sanctuary will be erected.

The steel is scheduled to go up the week of 9/15/08.

Thanks to the extremely generous people of Goodwill, we have now passed the 50% mark in collecting our pledges even though we are only in the 15th month of a 36 month pledge campaign. We have now collected $572,096.00 of the $1,142,137.00 that was pledged.  

Throughout this process we continually enjoy a great outpouring of Gods amazing grace, love, faithfulness and provision. So far, every need has been met. Everytime that it seems we could experience a shutdown in the project, God provides a way. We stand amazed at what He has done so far. We give Him all the Glory!    